Installation

1. Turn off the power to the Y-200.

2. Open the front cover of the Y-200.

3. Open the “Display and Keypad” door to gain

access to the Y-200 Control Board and Lon-
Works Module mounting location.

4. Plug LonWorks Module onto the P1 & P2 con-

nectors on the Y-200 Control Board. (See dia-
gram below.)

5. Connect communication cabling to the 2-pin

connector J13 (LonWorks connection). (See dia-
gram below.)

6. Install conduit as appropriate for connection of

communication cabling.

For LonWorks Communications
Cabling

Use cable and installation techniques as specified in
the LonWorks controller documentation.