FUNCTION OF THE GEMINI

The water in the heating tank A, is maintained
at the same level at all times by a sensor
called the water level probe B. This controls
the water inlet valve C.
When the brew switch is pushed, a brew cycle
starts: The dump valve D, is opened by the
brew timer E, allowing hot water to be sprayed
over the ground coffee for a specific time
period .
Brewed coffee then pours from the brew cone
F, into the Satellite.
The hot water faucet G, dispenses hot water
for tea, instant beverages, or soups and can

be used at any time without interrupting the brew cycle. A warmer element, H, keeps the coffee in
the Satellite at the proper temperature.

1234567890123456789012345678901212345678901234

1234567890123456789012345678901212345678901234

1234567890123456789012345678901212345678901234

1234567890123456789012345678901212345678901234

1234567

1234567

1234567

1234567

1234567

1234567

1234567

1234567

1234567

1234567

12

H

SETUP INSTRUCTIONS

1. Locate a position for the Gemini 120A on a firm and level, counter top.
2. Remove the top cover of the brewer and lid from the heating tank. Hand fill the tank until the

water level is approximately two (2) inches below the probe tip.

3. A 1/4" female flare fitting is required for water supply. Connect the water line to the inlet valve

fitting and turn on the water.

4. With the top cover removed, turn thermostat stem clockwise until it stops.
5. Plug the unit into a power supply outlet and turn toggle switch on. Turn ON/OFF switch to ON

position. Make sure water is flowing into the heating tank. Filling should stop when the water
level reaches the probe tip. When this is verified, replace both tank lid and top cover to the
machine.

6. Allow 15 to 20 minutes for the water in the tank to reach brewing temperature. The

BREW READY light will come on when it reaches the correct temperat

ure.

123

123

A

E

G

F

D

B

C

NOTICE
This brewer must be installed by a professional licensed technician and must comply with all local
electrical, mechanical and plumbing codes having jusrisdiction. Wilbur Curtis Company will not
accept any responsibility if these conditions are not met. This machine must be used for it's in-
tended purpose and the function for which it was designed.

All products manufactured by the Wilbur Curtis Company are thoroughly inspected at the factory
and are warranted to be free of all defects or faulty workmanship. The Gemini unit is packaged for

maximum protection while being shipped.
Make sure the shipping carton is not damaged
or punctured. Unpack the carton carefully,
inspecting the contents for any damage that
may have occurred in transit. Report any
damage immediately to the freight company.

UNPACKING

GEMINI 120A

12

12

Advertising