STARTING
Prior to starting the device, the system and process-specific safety measures must be observed. For
the media to be supplied, the relevant safety requirements and measures must be taken into account.
W A R N I N G !
Before starting up check whether the mains power supply
voltage corresponds with the information stated on the
nameplate.
W A R N I N G !
Start up only the built-in heated probe tube because otherwise
there is a risk of burning !
The following step-by-step procedure is recommended :
Check temperature set value at external controller. Thereto remove lid of the connection box.
Switch on mains power supply.
The heated sample tubes are ready for operation after 2 hours heat-up time.