INSTALLATION –

TOOLS NEEDED:
One (1) pipe wrench and one (1) socket wrench.

STEP 1 - Preparation

A

Drain the water in the receiving tank to a level
which is below the control opening (A). Allow the
boiler to cool to 80˚F (27˚C) and allow the
pressure to release to 0 psi (0 bar).

C

D

Use a socket wrench to secure the feeder (D)
to the receiver tank with the six

3

/

8

” - 16

bolts through mounting flange (C) and
tighten to 18 ft•lb (24 N•m).

STEP 2 - Install the Control Unit

Mounting Flange Dimensions

B.C

.

O.D.

Float

O.D.

B.C.

C

D

Diameter

6

11

16

(170) 5

3

4

(146)

6

7

16

(11.1)

4

3

4

(121)

Series 851, 851-S and 847

Dimensions, in. (mm)

“C” - number of mounting holes
“D” - size of mounting holes