Figure e-3. bearing installation – Gorman-Rupp Pumps 14C2-B 740693 and up User Manual

Page 29

Advertising
background image

OM-00670

10 SERIES

MAINTENANCE & REPAIR

PAGE E - 7

tation is rough or the bearing balls are discolored,
replace the bearings.

The bearing tolerances provide a tight press fit
onto the shaft and a snug slip fit into the pedestal.
Replace the bearings, shaft, or pedestal if the
proper bearing fit is not achieved.

If bearing replacement is required, use a bearing
puller to remove the inboard and outboard bear­
ings from the impeller shaft.

Shaft and Bearing Reassembly
and Installation

Clean and inspect the bearings as indicated in
Shaft and Bearing Removal and Disassembly.

To prevent damage during removal from
the shaft, it is recommended that bearings
be cleaned and inspected in place. It is
strongly recommended that the bearings
be replaced any time the shaft and and
bearings are removed.

Inspect the shaft for distortion, nicks or scratches,
or for thread damage on the impeller end. Dress
small nicks and burrs with a fine file or emery cloth.
Replace the shaft if defective.

The bearings may be heated to ease installation.
An induction heater, hot oil bath, electric oven, or
hot plate may be used to heat the bearings. Bear­
ings should never be heated with a direct flame or
directly on a hot plate.

NOTE

If a hot oil bath is used to heat the bearings, both the
oil and the container must be absolutely clean. If
the oil has been previously used, it must be thor­
oughly
filtered.

Heat the bearings to a uniform temperature no
higher than
250

_F (120_C) and slide the bearings

onto the shaft, one at a time, until they are fully
seated. This should be done quickly, in one con­
tinuous motion, to prevent the bearings from cool­
ing and sticking on the shaft.

Use caution when handling hot bear­
ings to prevent burns.

NOTE

Position the bearing (5) on the shaft as indicated by
the following illustrations.

INSTALLATION OF NEW DEPARTURE OR

BCA/FEDERAL MOGAL 5300W SERIES BEARINGS

(OPEN OR ENCLOSED IMPELLERS)

INSTALLATION OF MRC/SKF 5300M OR

FAFNIR 5300W SERIES BEARINGS

(OPEN OR ENCLOSED IMPELLERS)

LOADING

DIRECTION OF

THRUST

BALL LOADING

GROOVE POSITIONED

AWAY FROM IMPELLER

GROOVE

DIRECTION OF

THRUST

LOADING

BALL LOADING

GROOVE POSITIONED

TOWARD IMPELLER

GROOVE

Figure E-3. Bearing Installation

After the bearings have been installed and allowed
to cool, check to ensure that they have not moved
out of position in shrinking. If movement has oc­
curred, use a suitably sized sleeve and a press to
reposition the bearings.

If heating the bearings is not practical, use a suit­
ably sized sleeve and an arbor (or hydraulic) press
to install the bearings on the shaft.