ELECTRICAL TESTING

Make the electrical checks which follow to deter­
mine if pump malfunctions are being caused by
problems in the motor or in the motor cable.

Test Equipment

A volt/amp/ohmmeter and megohmmeter of ade­
quate range and quality are required to conduct
the electrical tests which follow.

Equipment

Use

Ammeter

To check AC Voltage
and current (amperage)

Ohmeter

To measure resistance
(ohms) to ground

Refer to the wiring diagram(s) accompany­
ing the motor and control box before re­
connecting any electrical leads which have
been disconnected. Connections to the
wrong terminals may damage the motor
and/or control devices.

Voltage Imbalance

Use a voltmeter to read each phase of the incom­
ing 3 phase power. Each phase must balance with
the other two as closely as can be measured with a
commercial instrument. If the phases are out of
balance, contact your power company. If the
phases are balanced, check out the motor as de­
scribed in the following steps:

a. Use a voltmeter, Amprobe, or equivalent in­

strument to read the voltage of incoming
power lines 1 and 2, 2 and 3, and 1 and 3 at the
control box. Voltage must match as closely as
can be measured. If possible, measure the
voltage at the control box with:

1. The pump shut off.
2. The pump running in air.

3. The pump submerged and running under

full load.

The voltage measured under each condition
must be the same.

b. If voltage is balanced when the pump is off but

is imbalanced when the pump is running,
thoroughly check the power source, all inter­
connecting cables, and the pump motor to
isolate the defect.

c. Use an Amprobe or equivalent instrument to

measure the current draw (amperage) of
each phase while the pump is running under
full load, and with no load. In each condition,
the amperage readings for all three phases
must match as closely as can be measured.
Normal amperage values are listed in Table 1,
Section B; these values apply only when the
voltage at the site is the normal voltage listed.

Motor and Power Cable Continuity

Set the megohmmeter at R x 1 scale and zero‐ba­
lance it. Test as follows:

a. Shut off incoming power to the control box,

and disconnect the motor power cable leads.
Connect the megohmmeter test leads to any
two power cable leads, and note the
megohmmeter reading. A high resistance
reading indicates an open or broken circuit in
the power cable or motor windings, or a bad
connection between the motor and cable.

b. Repeat Step a. with each set of leads. The

three readings shall be as close as can be
measured.

c. If readings indicate that continuity problems

exist in the motor or motor cable, the motor
must be returned to the factory or to a U/L‐ap­
proved facility.

Insulation Resistance

Set the megohmmeter at R x 100, and zero‐ba­
lance it. Test as follows:

a. Shut off incoming power to the control box,

and disconnect the motor power cable leads.
Connect one megohmmeter test lead to the
motor cable green/yellow ground lead. Touch

Advertising