1.0 Introduction, continued

1.1 Parts List

Please refer to the bill of material enclosed with each rack. Each battery rack is
unique and will contain different parts for each configuration

1.2 Pre-installation

Note:

The following items must be addressed prior to assembly and installation.

Installation Considerations

Anchoring

To provide stability and safety, securely anchor all battery racks
to the floor in accordance with applicable codes

Codes

Ensure observance of all applicable codes.

Grounding

Ground the rack in accordance with all applicable codes.

Location

Locate the racks in a clean, cool, dry place where they will not
be affected by sources of heat or sunlight. Adequate ventilation
must be provided. DO NOT install the rack in an airtight
enclosure or room with no ventilation. The floor must be level,
and capable or supporting the weight of the battery rack and the
batteries, in addition to any other equipment.

Battery Installation Procedure

DO NOT install batteries until the rack has been properly and
completely installed. Know the polarities and terminal
placement of each battery and coordinate its location prior to
installation. Unless otherwise instructed, begin the installation
of the batteries at the center of the bottom row and work out to
each end. Install the batteries on the lowest shelves first and
work upward. If necessary, use only a small amount of water or
unscented talcum powder to help reduce friction on the
shelving. DO NOT use any lubricating agent to help slide
batteries into place.

Seismic/Earthquake Protected
Design

Perform in accordance with applicable local, state and national
codes.

Maintenance

Make periodic inspections of the entire rack for any signs of acid
corrosion. If found, the acid must be neutralized. If left
unattended, the corrosion could weaken areas of the rack.
Periodically check to see If the rack remains properly grounded
and anchored.