18
STAGE 5
COMMISSIONING THE CONTROL PANEL
5.1 - Initial Wiring & Control Panel Setup
1.
CONNECT POWER TERMINALS L1 - L2
AND A SUITABLE EARTH (L2 BEING LIVE!)
2.
SELECT THE MOTOR POWER SETTING ON
THE TRANSFORMER TO LEVEL 1 FOR
COMMISSIONING
Fig 16
Fig 17
Fig 18
3.
SELECT DIPSWITCHES 1 & 2 OFF FOR
COMMISSIONING
4.
ENSURE HARD WIRE LINK IS FITTED
BETWEEN TERMINALS 1 & 2 AND
2 & C1
L1 L2 U V W E1 ES 10 11 1 2 3 5 7 C1