VI. SHUTDOWN

1. Shutoff inlet block valve.

2. Allow

suffi cient time for the line pressure down-

stream of the inlet block valve to bleed down.

3. Shutoff the outlet block valve.

4. Relieve any trapped upstream and downstream

pressure and loading pres sure from PGR-1.

5. The regulator may now be removed from the

pipe line or disassembled for inspection and pre-
ven ta tive main te nance while in-line.

VII. MAINTENANCE

SECTION VII

A. General:

1. The main regulator body may be serviced

without re mov ing the regulator from pipeline.
The reg u la tor is designed with quick-change
trim to simplify maintenance.

2. Record the name plate information to req-

ui si tion repair parts for the regulator. This
in for ma tion should include: Serial Number
and Product Code.

3. Refer to Section IX for recommended repair

parts. Only use original equipment parts
sup plied by Cashco for re build ing or re pair-
ing reg u la tors.

4. Owner should refer to owner's procedures

for removal, handling, cleaning and disposal
of nonreuseable parts, i.e. gaskets, etc.

NOTE: On regulators originally supplied as
“special clean” – Opt-56, maintenance must
include a level of cleanliness equal to Cashco
cleaning standard #S-1542.

5. The Inner Trim is re moved and replaced back

in the body (1) as an assemblage of parts.
The Inner Trim Assembly, here in af ter called
ITA, consists of following parts: (See Figure
1)

A detailed view of the dynamic side seal
parts is shown on page 5.

WARNING

SYSTEM UNDER PRESSURE. Prior to per form ing any
maintenance, isolate the reg u la tor from the system and
relieve all pressure. Failure to do so could result in per-
sonal injury.

SECTION VI

B. Main Valve Disassembly:

1. Shut down system in accordance Section

VI.

2. Disconnect the external sensing line from

the pilot valve sensing port.

3. Though it is possible to disassemble the

valve unit while installed in a pipeline, it is
rec om mend ed that all maintenance be done
in a shop. The instructions hereafter will as-
sume in shop disassembly. Remove valve
from pipeline.

4. Place the main valve unit in a vise with the

cover dome (2) upwards.

5. Loosen all fi tings and remove tubing that

connect the inlet fi lter to the stablizer, the
cover dome to the metering valve and the
outlet of the metering valve to the outlet of
the body.

6. Loosen and remove the two nuts (24) that

secure the mounting bracket (3) and pilot to
the cover dome (2). Set pilot assembly aside.
Place match marks on the cover dome fl ange
to mark the location for the mounting bracket
and two longer bolts (23).

Item Dynamic

No.

Seal Type

Part Description

4

.......................All....................................................Cage

5........................All......................................................Plug
9

...................... All

.....................................Guide

Bearing

10......................All......................................................Seat

13 ..................... All ................................. Static Stem Seal

13.1 ............... All ...................... Upper Static Stem Seal

13.2 ............... All ......................Middle Static Stem Seal

13.3 ............... All ...................... Lower Static Stem Seal

14

......................All..................................Cage O-ring Seal

15......................OR...........................Dynamic O-ring Seal

15.1...............UC............................Dynamic U-cup Seal

15.2............... UC.......................................Seal Retainer

Advertising