INSTALLATION

1. Mount the push button control panel (B) so bottom

of control panel-to-dock floor distance (C) is 48 in.

(1219.2 mm).

2. Install electrical disconnect panel (A) if not already

installed. (Disconnect panel can be a small snap

switch as current will be minimal.

3. Install and connect the control wiring.

4. Re-install the air bellows, and connect air line.

5. Connect the dock leveler power cable coil. Refer

to the electrical drawings supplied with the dock

leveler.

6. After all electrical connections in the pit have been

made, raise the leveler, disengage the maintenance

prop and allow the platform to lower.

Install Control Panel and Wiring

A— Disconnect Panel

B— Control Panel

(Provided by others)

C— Distance, 48 in. (14 630 mm)

The electrical power must be OFF prior to electrical

installation. For maximum protection, use an OSHA

approved locking device to lock out all power

sources. Only the person installing the equipment

should have the key to unlock the power source.

Failure to follow these instructions may result in

serious personal injury or death.

DO NOT make any final electrical connections until

all welding has been completed. Failure to do this

may result in serious personal injury or death.

All electrical work — including the installation of

the disconnect panel, control panel, and final

connections to the pit junction box — must be

performed by a certified electrician and conform to

all local and applicable national codes.