2-E: Recommended Installation Sequence:
After pit is completed, follow this sequence:
Measure pit squareness, depth, width, and length against certified prints
Measure cast-in anchors, pier elevation on all piers against certified prints
Dimensions MUST be correct before installing scale hardware
Using packing list, be sure all scale elements/parts have arrived intact and Undamaged
Then install:
Base Plate Assemblies
Check Stands
Wood blocking and cribbing
Weighbridge Steel
Weighbridge Sections
Load Cell Flexure Assembly
Adjusting Elevation
Leveling Load Cell Flexure Assemblies
Grouting Load Cell Baseplates
Checkrods
Grouting Check Stands
Check Rod Adjustment
Deck coping, manholes, deck forming, deck rebar
Grounding
Rail and anti-creep devices
Form and pour concrete deck
When deck is cured, install:
Complete wiring of load cells
Instrumentation and any peripheral equipment
Calibration and testing