DO NOT SCALE DRAWING

DATE: 2/13/07

DRAWN BY: AFS

DO NOT SCALE DRAWING

STEELCRAFT PRODUCTS

P.O. Box 90365 - Pasadena, CA 91109
PHN 626-798-7401 FAX 626-798-1482

MODEL

AB-50P

BASEBALL BACKSTOP

NOTE: SPECIFICATIONS ARE SUBJECT TO CHANGE

9. REPEAT THIS PROCEDURE ALTERNATING FROM RIGHT TO LEFT. CHECK AS YOU

PROCEED TO MAKE SURE THAT THE FRONT ARCH IS PLUMB. IT IS BEST TO HAVE THE

ARCH SLIGHTLY LAID BACK RATHER THAN LEANING TO THE FRONT. PLUMB IS IDEAL.

10. AFTER ALL RIBS ARE IN PLACE, MAKE SURE ALL THE JOINTS ARE SEATED ON ALL RIBS

AND ARCH CONNECTIONS. ALIGN EVERYTHING TO THE BEST OF YOUR ABILITY.

TIGHTEN THE SET SCREWS ON THE FRONT ARCH WITH A WRENCH AND EXTENSION BAR.
DON’T TIGHTEN THE SET SCREWS FOR THE RIBS YET.

11. INSTALL THE HORIZONTAL STIFFENERS APPROXIMATELY 5’-0” ABOVE GRADE. START

WITH THE SHORT ONES BETWEEN RIBS 4 AND 5. ATTACH THE BEGINNING END WITH A

BRACE BAND AND BOLT w/ NUT. THE INSIDE CONNECTION USES SPLIT BRACE BANDS

AND BOLT w/ NUT. DO NOT TIGHTEN BOLTS UNTIL ALL THE STIFFENERS ARE IN PLACE.

12. INSTALL THE ANCHOR BOLTS AND NUTS IN THE HOLES IN THE BOTTOM ARCH. THREAD

THE NUTS ONTO THE ANCHOR BOLTS UNTIL ONE THREAD IS SHOWING.

13. PLACE THE MAIN FOOTING ANCHORS IN THE FOOTING HOLES AND INSERT THEM INTO

THE OPEN ENDS OF THE FRONT ARCH. TIGHTEN THE SET SCREWS WITH A HAMMER AND

WRENCH.

14. POUR CONCRETE IN THE FOOTING HOLES. THE MAIN FOOTING HOLES SHOULD BE

POURED TO WITHIN 2” OF FINISHED GRADE. THE ANCHOR BOLT HOLES CAN BE
POURED UP TO FINISHED GRADE. WAIT AT LEAST 72 HOURS BEFORE ATTACHING THE

FABRIC.

15. NOW THE FUN BEGINS. THERE ARE TWO ROLLS OF FABRIC EACH AT 9 ga. 12’ X 50’.

LOCATE THE TENSION BARS AND TENSION BANDS AND OTHER MISCELLANEOUS

FENCING HARDWARE.

16. THE CIRCUMFRENCE AT THE BASE OF THE ARCH IS 60 ft. YOU WILL HAVE TO WEAVE 10

ft FROM ONE ROLL ONTO THE OTHER 50 ft ROLL TO GET THE FIRS COURSE. STAND THE

WIRE ON EDGE AND PLACE THE FABRIC SO IT IS CENTERED ON THE OUTSIDE OF THE

FRAME AND JUST ENOUGH ABOVE THE BOTTOM ARCH SO THE TENSION BARS CAN BE

INSTALLED. PUT TIE WIRES ON THE CENTER RIB AND THE FABRIC. STRECH THE FABRIC

AROUND THE BOTTOM AS BEST AS YOU CAN AND INSTALL THE TENSION BARS IN THE
BOTTOM AND ATTACH BARS TO TENSION BANDS.

17. WHEN THE BOTTOM COURSE IS SUFFICIENTLY TIGHT, INSTALL TENSION BARS AND BANDS

ON THE FRONT ARCH AND CUT THE EXCESS FABRIC OFF ON THE BIAS. THE BOTTOM OF

THIS COURSE WILL BE EASILY STRECHED AND THE TOP WILL NOT BE REAL TIGHT. IT WILL

REQUIRE A BIAS CUT ON THE TOP OF THE COURES WHERE IT MEETS THE FRONT ARCH.

IT DOESN’T GET EASIER THAN THIS.

18. PLACE THE REMAINDER OF THE FABRIC IN THE CENTER OF THE BACKSTOP LIKE ABOVE.

SLIDE IT UP THE BACKSTOP UNTIL IT IS CLOSE TO THE FRONT ARCH. THERE SHOULD BE

AMPLE OVERLAP OVER THE FIRST COURSE OF FABRIC. STRECH THIS COURSE AS BEST

YOU CAN AND HOG TIE THE OVERLAP TO THE BOTTOM COURSE. THIS COURSE WILL

HAVE TO BE BIAS CUT AT THE ENDS BEFORE THE TENSION BE INSTALLED.

19. TIE THE FABRIC TO THE RIBS USING TIE WIRE. CLEAN UP AND YOU ARE DONE.