OPERATING YOUR 25176B

1. Inspect the 25176B thoroughly to insure that it is

in good operating condition.

2. Make sure all connections are correct and tight

(see set-up diagram below).

3. Open the liquid port of the recovery cylinder

(always open valves slowly to check hoses and
connections for leaks).

4. Make sure the Recover/Purge valve is set on

Recover.

5. Open the output port of the 25176B

6. Open the liquid port on your manifold gauge set;

opening the liquid port will remove the liquid from
the system first, greatly reducing the recovery
time. (after the liquid has been removed, open the
manifold vapor port to finish evacuating the
system).

7. Connect your 25176B to a 220/240V outlet.

a. Switch the main power switch to the ON position.

You should hear the fan running.

b. Press the compressor start switch. This “momen-

tary” switch will start the compressor. It may be
necessary, under certain circumstances, to press
this switch more than once to start the compres-
sor.

8. Slowly open the input port on the 25176B.

a. If the compressor starts to knock, slowly throttle

back the input valve until the knocking stops.

b. If the input valve was throttled back, it should be

fully opened once the liquid has been removed
from the system (the manifold gauge set vapor
port should also be opened at this time).

9. Run until desired vacuum is achieved.

a. Close the manifold gauge sets vapor and liquid

ports.

b. Close the 25176B input port.
c. Shut off and proceed with the Self Purge

procedure on the next page.

Note: Always purge the 25176B after each use (see
Self Purge procedure on page 12). Failure to purge
the remaining refrigerant from the 25176B could
result in the acidic degradation of internal compo-
nents, ultimately causing premature failure of the unit.

PROCEDURE FOR NORMAL SYSTEM RECOVERY

THIS IS THE FASTEST METHOD FOR RECOVERING

VAPOR REFRIGERANT

OPTIONAL MOISTURE

SIGHT GLASS

A SCALE MUST BE USED TO AVOID

OVER FILLING THE STORAGE TANK

MANIFOLD

GAUGE

SET

SYSTEM BEING

SERVICED

LIQUID

ƽ

VAPOR

LIQUID

OUTPUT

INPUT

11

First turn knob to liquid

port. When liquid is

removed, move to full

open for vapor

DIAGRAM FOR REFRIGERATION RECOVERY