20

UPC5000/UPC5010 Operation & Maintenance Manual

7. Install all tubing sections that attach to the ORION-2C manifold.

8. Install the nitrogen cylinder and its associated tubing.

9. Fill the cylinder to approximately 1000 PSIG and check all fittings for leaks. If there are no leaks, fill

nitrogen supply cylinder to 2200 PSIG. See Section 2.1 on page 3 for cylinder refilling procedure.

10. Install panel/chassis assembly in its enclosure as described in Table 4.2.1 on page 14.

4.2.10

ORION-2C Manifold, Valve Adjustment Procedure

Tools required:

hex wrench (.050")
hex wrench (.061")

NOTE:

See Table 4-7 on page 32 and Figure 4-1 on page 33 for additional parts information. * denotes reference to

Figure 2-2 on page 4.

1. If not already done, remove the ORION-2C

COARSE

and

VENT

valve knobs (3) using the .061" hex

wrench.

2. Energize the unit and let it warm up. Turn the

RANGE SELECT

switch to its highest range. To adjust the

coarse valve, go to step 3.

3. Using a .050" hex wrench, loosen the set screw (34) on the locknut (2) and turn the locknut clockwise to

its stop.

4. Check to see that the knob insert (4) is securely fastened to the valve shaft (11). If it is loose, re-tighten

the set screws (23) with the .061" hex wrench.

5. Close the

COARSE

valve by turning the knob insert (4) clockwise until you feel the valve needle seat on

the O-ring (valve is now in the closed position).

6. Rotate gears (6) on both

ISOLATION

valves (two inner valves), counter-clockwise until they stop, then

rotate clockwise 1/2 turn (opening isolation valves).

7. Use the

PRESSURE LIMIT CONTROL

(*1), to increase the supply pressure to between 80% and 100% of

full scale.

8. Open the

VENT

valve (*8) to atmosphere, zero the indicator (press

ZERO

switch [*12] less than 5

seconds), then close the

VENT

valve (*8).

9. Slowly open the

COARSE

valve by turning the knob insert (4) counter-clockwise until you notice the

displayed pressure increase. Then turn the knob insert slightly clockwise until the pressure stops rising.

10. Mark a radial line at the 12 o'clock position on the knob insert.

11. Turn the knob insert (4) clockwise to move the mark to the 6 o'clock position.

12. Turn the locknut (2) counter-clockwise until it contacts the bottom of the stop washer. Tighten the set

screw (34) on the locknut with the .050" hex wrench.

13. Install the

COARSE

valve knob (3) on the knob insert (4) and engage its gear (5) with the smaller

isolation valve gear (6). Turn the knob clockwise until the isolation valve is slightly snug.

Do not use excessive torque when adjusting valve. The seat can be damaged.

14. Remove the

COARSE

valve knob. Align the set screws (25) with the indentations on the knob insert

Install the knob on the knob insert while engaging the knob gear (5) with the isolation valve gear (6).

15. Tighten the set screws (25) with the .061" hex wrench. The

COARSE

valve is now adjusted.

Transducer Wires

Terminal Block Wires

+ Excitation

TB1-4 (Green wire)

- Signal

TB1-6 (Red wire)

+ Signal

TB1-5 (White wire)

- Excitation

TB1-7 (Black wire)

Table 4-2. Transducer Wire to Terminal Block Wire Connections

!

Caution