Condec UPC5010 User Manual
Page 23

20
UPC5000/UPC5010 Operation & Maintenance Manual
7. Install all tubing sections that attach to the ORION-2C manifold.
8. Install the nitrogen cylinder and its associated tubing.
9. Fill the cylinder to approximately 1000 PSIG and check all fittings for leaks. If there are no leaks, fill
nitrogen supply cylinder to 2200 PSIG. See Section 2.1 on page 3 for cylinder refilling procedure.
10. Install panel/chassis assembly in its enclosure as described in Table 4.2.1 on page 14.
4.2.10
ORION-2C Manifold, Valve Adjustment Procedure
Tools required:
hex wrench (.050")
hex wrench (.061")
NOTE:
See Table 4-7 on page 32 and Figure 4-1 on page 33 for additional parts information. * denotes reference to
Figure 2-2 on page 4.
1. If not already done, remove the ORION-2C
COARSE
and
VENT
valve knobs (3) using the .061" hex
wrench.
2. Energize the unit and let it warm up. Turn the
RANGE SELECT
switch to its highest range. To adjust the
coarse valve, go to step 3.
3. Using a .050" hex wrench, loosen the set screw (34) on the locknut (2) and turn the locknut clockwise to
its stop.
4. Check to see that the knob insert (4) is securely fastened to the valve shaft (11). If it is loose, re-tighten
the set screws (23) with the .061" hex wrench.
5. Close the
COARSE
valve by turning the knob insert (4) clockwise until you feel the valve needle seat on
the O-ring (valve is now in the closed position).
6. Rotate gears (6) on both
ISOLATION
valves (two inner valves), counter-clockwise until they stop, then
rotate clockwise 1/2 turn (opening isolation valves).
7. Use the
PRESSURE LIMIT CONTROL
(*1), to increase the supply pressure to between 80% and 100% of
full scale.
8. Open the
VENT
valve (*8) to atmosphere, zero the indicator (press
ZERO
switch [*12] less than 5
seconds), then close the
VENT
valve (*8).
9. Slowly open the
COARSE
valve by turning the knob insert (4) counter-clockwise until you notice the
displayed pressure increase. Then turn the knob insert slightly clockwise until the pressure stops rising.
10. Mark a radial line at the 12 o'clock position on the knob insert.
11. Turn the knob insert (4) clockwise to move the mark to the 6 o'clock position.
12. Turn the locknut (2) counter-clockwise until it contacts the bottom of the stop washer. Tighten the set
screw (34) on the locknut with the .050" hex wrench.
13. Install the
COARSE
valve knob (3) on the knob insert (4) and engage its gear (5) with the smaller
isolation valve gear (6). Turn the knob clockwise until the isolation valve is slightly snug.
Do not use excessive torque when adjusting valve. The seat can be damaged.
14. Remove the
COARSE
valve knob. Align the set screws (25) with the indentations on the knob insert
Install the knob on the knob insert while engaging the knob gear (5) with the isolation valve gear (6).
15. Tighten the set screws (25) with the .061" hex wrench. The
COARSE
valve is now adjusted.
Transducer Wires
Terminal Block Wires
+ Excitation
TB1-4 (Green wire)
- Signal
TB1-6 (Red wire)
+ Signal
TB1-5 (White wire)
- Excitation
TB1-7 (Black wire)
Table 4-2. Transducer Wire to Terminal Block Wire Connections
!
Caution