The Discharge Pipe:

• Shall not be smaller in size than the outlet pipe size of the valve, or

have any reducing couplings or other restrictions.

• Shall not be plugged or blocked.
• Shall not be exposed to freezing temperatures.
• Shall be of material listed for hot water distribution.
• Shall be installed so as to allow complete drainage of both the relief

valve and the discharge pipe.

• Must terminate a maximum of six inches above a floor drain or

external to the building. In cold climates, it is recommended that the

discharge pipe be terminated at an adequate drain inside the building.

• Shall not have any valve or other obstruction between the relief valve

and the drain.

Once the boiler is installed and filled with water and the system

is pressurized, manually test the operation of the pressure relief

valve. See the maintenance section of this manual for instructions.
Your local code authority may have other specific safety relief

valve requirements not covered below. If any pressure relief valve

is re placed, the replace ment valve must com ply with the current

version of the ASME Boiler and Pressure Vessel Code, Section

IV (“HEATING BOILERS”).
VW HOT WATER SUPPLY BOILERS, are shipped with a 125 psi

(860kPa) pressure relief valve that must be in stalled in the water

out let as near to the boil er as possi ble.

This ASME-rated valve has a discharge capacity that exceeds maximum

boiler input rating and a pres sure rating that does not exceed maximum

working pres sure shown on boiler rating plate. In addition, a CSA

design-certified and ASME-rated tempera ture and pressure (T&P)

relief valve must be installed on each and every water storage tank

in hot water supply system. The T&P relief valve must comply with

appli cable construction provisions of Standard for Relief Valves for

Hot Water Supply Systems, ANSI Z21.22 or CSA 4.4. T&P re lief valve

must be of automatic reset type and not embody a single-use type

fusible plug, cartridge or linkage.
T&P relief valve should have a temperature rating of 210°F (99°C),

a pressure rating not exceeding lowest rated working pressure of

any system compo nent, and a discharge capacity exceeding total

input of water boilers supply ing water to storage tank.
Locate the T&P relief valve (a) in the top of the tank, or (b) in the side of

the tank on a centerline within the upper 6 inches (152mm) of the top

of the tank, see Figures 14 and 15. The tapping should be threaded in

accordance with the current edition of the Standard for Pipe Threads,

General Purpose (inch), ANSI/A SME B1.20.1. The location of, or in-

tended location for, the T&P relief valve should be readily accessible for

servicing or replacement.
VB HOT WATER HEATING BOILERS, are shipped with a 50 psi

(345kPa) pressure relief valve. This relief valve must be in stalled

in the water outlet as near to the boiler as possi ble.

GENERAL

REQUIRED ABILITY

INSTALLATION OR SERVICE OF THIS BOILER REQUIRES

ABILITY EQUIVALENT TO THAT OF A LICENSED TRADES MAN

IN THE FIELD INVOLVED. PLUMBING, AIR SUPPLY, VENTING,

GAS SUPPLY, AND ELECTRICAL WORK ARE RE QUIRED.

LOCATION

When installing the boiler, consideration must be given to proper

location. The location selected should provide ade quate air supply

and be as centralized with the piping system as possible.

If the boiler is installed above radia tion level, a

Low Water

Cutoff Device must be installed in the boiler outlet at the time of

installation.

PANELS AND COVERS

All panels and covers (e.g. control and junction box covers;

front, side and rear panels of boiler, see Figure 8) MUST be in

place after service and/or before opera tion of the boiler. This

will ensure that all gas ignition components will be protected

from water.

The VF is a low-pressure boiler (Category IV) to be used as either

hot water supply (domestic/commercial water heating) or hot water

heating (hydronic) application. Category IV boilers oper ate with a

positive vent pressure and with a vent gas tempera ture less than

120°F (49°C) above its dew point. Category IV appli ances are

often termed “High Effi ciency” appliances.