INSTALLATION

Pre-Plan your installation. You will need to accomplish the following:

▪

Meet all National and Local codes. (NEC

®

Article 285 addresses SPDs)

▪

Mount SPD as close to panel or equipment as possible to keep leads short.

▪

Ensure leads are as short and straight as possible, including neutral and ground.

Consider a breaker position that is closest to the SPD and the panel’s neutral & ground.

▪

Suggested breaker & conductor size is 60A-30A with 6 AWG.

▪

Make sure system is grounded per NEC

®

and clear of faults before energizing SPD.

The following options or implementations require extra consideration. See appropriate sections

within this manual:

▪

Internal or Integral Mount Installation inside electrical gear (page 5)

▪

Flush Mount Option (page 6)

▪

Retro-fit where no breaker positions are available (page 6)

▪

UL/NEMA 3R Drain Holes (page 6)

1. Use a voltmeter to check all voltages to ensure correct SPD.

2. If SPD has Dry Contact, Remote Monitoring or Remote Display, pre-plan their installation.

3. Remove power for panel. Confirm panel is deenergized.

4. Identify connection/breaker location and SPD location.

5. Make sure leads are short! Reducing inches matter! Pretend that connector leads cost you

$1000/foot to make leads short!

6. Remove an appropriately sized knockout from panel. Create an appropriately sized hole in the

SPD enclosure.

7. Mount SPD.

8. Connect conductors as appropriate – short and straight as possible

(Note that Hi-Legs are Phase B).

9. Label or mark conductors as appropriate (neutral: white, ground: green, energized:

black, hi-leg: orange).

10. Make sure system is bonded per NEC

®

and is clear of hazards or faults before energizing.

(N-G bonding not per NEC

®

will fail SPDs: #1 cause of SPD failures.)

11. Energize and confirm proper operation of indicators and/or options.

Figure 7

TYPICAL PANEL INSTALLATION

A

B

C

G

N

BREAKER

Phase C

Service

Phase B

Phase A

Surge Counter

Advanced Protection Technologies

Silence

Test

Count

Reset

▪

Use closest breaker to SPD

▪

Locate SPD close to intended breaker

▪

Keep Leads Short as Possible

▪

Avoid Sharp Bends

▪

Outdoor installation requires appropriate

weather sealing at nipple (o-ring, sealing

conduit, etc.)

To Protected Loads