means that the path cannot receive I/Os. A path will go into the offline status

for the following reasons:

An error occurred on the path.

A user intentionally placed the path offline by using the Path Management

window in the HDLM GUI.

A user executed the HDLM command's offline operation.
For details on the offline operation, see

offline (Places Paths Offline) on

page 6-6

.

Hardware, such as cables or HBAs, has been removed.

For details on path statuses and the transitions of those statuses, see

Path

Status Transition on page 2-20

.

Automatic Path Switching

The following describes the automatic failover and failback functions, which

automatically switch a path.

Automatic Failovers

If you detect an error on the path that is currently being used, you can

continue to use the system by having the status of that path automatically

changed to offline, and then automatically have the system switch over to

another online path. This functionality is called automatic failover. Automatic

failovers can be used for the following levels of errors:

Critical

A fatal error that might stop the system.

Error

A high-risk error, which can be avoided by performing a failover or some

other countermeasure.

For details on error levels, see

Filtering of Error Information on page 2-34

.

When the Thunder 9500V series, or Hitachi AMS/WMS series is being used,

HDLM will select the path to be used next from among the various paths that

access the same LU, starting with owner paths, and then non-owner paths.

For example, in

Figure 2-10 Path Switching on page 2-18

, the owner

controller of an LU is CHA0, and access to the LU is made via only one path

(A). After that access path (A) is placed offline, the first choice for the

switching destination is the other path connected to CHA0 (B). If an error

also occurs on that path (B), then the next possibility for a path comes from

one of the two paths (C or D) connected to CHA1.

When the Lightning 9900 series, Lightning 9900V series, Hitachi USP,

Universal Storage Platform V/VM, Virtual Storage Platform, Hitachi AMS2000

series, or Hitachi SMS is being used, all the paths are owner paths. This

means that all the paths that are accessing the same LU are possible

switching destinations. For example, in

Figure 2-10 Path Switching on page

2-18

, the LU is accessed using only the one path (A). However, after that path

HDLM Functions