Planning Location

Allow enough space for the tape library. Plan the signal cable and power cable
routing. Provide enough space to open all the doors.

Provide 15 centimeters (6 inches) above the tape library and 10 centimeters (4
inches) on the sides for cooling clearance.

Figure 2-1

shows the space needed for the tape library.

Figure 2-2

shows the locations for power and signal cable routing.

Follow the site guidelines detailed in the L700 Tape Library Installation Manual.

Figure 2-2. Power and Signal Cable Routing

Note.

To ensure reliable operation, place the tape library in an environment that is free of dust

and excessive humidity.