MACHINE SET UP / INSTALLATION

1. Machine assembly / set up installation:

1.1 Saw base / pedestal:

1. Remove preassembled base from shipping container. Check for loose parts and

discard container.

1.2 Saw assembly:

1. Carefully remove the saw from the shipping container. Take care not to damage any

components, check for any loosen items. Discard container.

1. Machine Placement:

1.3 Anchoring the machine:

NOTE: Machine must be located away from, congested areas, traffic areas, close

proximity to where others will be working!

Bandsaw should always be positioned so operator can be accessible to all sides and

that there are no trip hazards or liquids present. Keep sides of saw area clear so there is

enough room to feed material into the saw. Keep the back of the saw 32” away from

walls.

Saw must be anchored on a level hard surface! Machine must be removed from the

pallet. Anchoring of the machine must be done to prevent movement of the unit during

operation. The base is supplied with two mounting holes one on the front and one on the

rear of the saw. (Figure 1) Anchoring must be done in a suitable fashion.