EUROMATIC 370 PP / S MAINTENANCE SCHEDULE

FERROUS HEAD

370PP /S

A: Gear box. Maintain safe level of oil. Oil should be visible through sight glass on the right side of the gear box

when machine is running. Note: Oil will appear foamy during operation.

When running at high speed oil may weep from

filler cap. This is normal and will subside once machine has expelled out the excess oil in gear box.


B: Air oiler Located on the air regulator.

Air must be dry and clean. Use appropriate measures to

insure this, before it enters the machine.

WARNING!!!!!

LOCK OUT AIR SUPPLY TO THE MACHINE BEFORE REMOVING OIL RESIVOIR PLUG.

C: Head feed cylinder. The oil reservoir is mounted into the cylinder. The reservoir is clear and you can visually

inspect the amount. When oil level is approximately a depth of 1/4” oil must be added

To fill reservoir, remove brass cap on top and add oil into the reservoir until full cycle head to bleed.

D: Chip drawer. Located behind the front access door, This drawer pulls easily out for cleaning.

E: Coolant. This pan is located under chip drawer. The coolant should be kept clean. When coolant needs changing,

remove the drain plug from the pan.

F: Way Oiler. This reservoir is on the back of the column. This reservoir should be kept topped off. At the beginning

of each shift, this should be pumped twice to maintain good lubrication for the ways.

G: Gib blocks. This acts as an adjustable guide for the gear box. If adjustment is needed

See the gib block adjustment section in this manual

H: Vise gib can be adjusted by loosening the lock nuts and turning the set screws equally.

This should be done when ever vise shifts left or right when clamping.

I: Chip brush. Replace as needed.

J: Excessive backlash. This can be reduced, by removing the spindle shaft cover plate on the lower right hand side of

the gear box. Using the set screws in plate, loosen mounting bolt and tighten set screws tightening these set screws will pull the

plate away for gear box and allow removal of the plate. With plate removed tighten spindle nut and replace plate in reverse

order. Proper backlash will be approximately. 1/16” to 1/8” play in spindle with blade on the spindle.

Maintenance Schedule

Item

Model

Daily

Weekly

Monthly

100 Hours

6 Months

Gear Box Oil

370 PP / S

change after first

change

Air Regulator oiler

370 PP / S

check / add

Head Feed Cylinder Oil

370 PP / S

add as needed

Coolant Water based

370 PP / S

check / add

change

Chip Drawer

370 PP / S

empty

Gib Adjustment (Head)

370 PP / S

check

as needed

Vise Gib Adjustment

370 PP / S

check

as needed

Way Oiler

370 PP / S

2 pumps

check / add

DRO Magnetic Strip

370 PP

wipe / clean

DRO Reader Adjustment

370 PP

check / set if needed

Lube Types

Head Feed Cylinder.-DTE 24

Hydraulic Oil