Powering On the Switch
To apply power to the AT-FS708 switch without the optional power cord
retaining clip installed, perform the following procedure:
1. Apply AC power to the switch by plugging the power cord into the AC
power connector on the back panel of the unit, as shown in
Figure 9.
Warning
Power cord is used as a disconnection device: To de-energize
equipment, disconnect the power cord.
5
Caution
Use only safety licensed power supply cord.
Figure 9. Connecting the AC Power Connector to Switch
2. Plug the other end or the power cord into a wall outlet.
3. Verify that the POWER LED is green. If the LED is OFF, refer to
4. Power ON the end-nodes connected to the switch.
5. Check that all the LINK/ACT LEDs are green. If any of the LEDs is
OFF, refer to “Troubleshooting” on page 32 for instructions.
The switch is ready for network operations.