6. Commissioning, operation

6.2 Electrical zero point (4 mA)

The zero point adjustment is made by an adjustment screw in the front, which,

depending on the instrument model, is accessible by loosening the window or the

locking screw. By turning the adjustment screw using a screwdriver the desired zero

point is set.
If the mechanical zero point has been altered via the

adjustment screw, the electrical zero point must be

matched again to the mechanical one.
For this, the differential pressure transmitter must first be

depressurised.
Remove the entire cable cover on the right-hand side

of the transmitter. To do this, undo the screw  on the

top of the cable cover cap  completely with a slotted

screwdriver (0.6 x 3.5 mm). Remove the screw. Pull the

cable cover , along with the socket insert , out from the

cable socket baseplate .

This isolates the transmitter from the voltage supply.
Take the cable cover cap  from the cable cap  and

push the socket insert  out, downwards, completely

through the cable cap .
Bridge contacts 5 and 6 on the socket insert with a

short length of wire, stripped at both ends (maximum

permissible resistance 30 Ω).
Reassemble the connector in the reverse order. Insert the

connector, with the piece of wire mounted, into the pin

insert . This remakes the voltage supply.
Within a max. of 30 seconds, the new zero point will be

saved within the electronics. During this time, the current in

the loop will rise to 9.5 mA.
The new zero point is maintained, even with a loss of

power, for an extended period.
Once more, disconnect the connector in the order

described above and remove the piece of wire. After again

assembling the connector, the electrical output signal will

once more match the display of the mechanical pointer.

Screw

Cable cover cap

Cable cover

Socket insert

Cable socket baseplate

Sealings

In order that the ingress

protection is maintained, the

seals  must be refitted.