HOT SURFACE IGNITION OPERATION SEQUENCE:

— A call for heat occurs from the building’s environment

control.

— 1-15 VDC is sent from the SmartBox

variable rate

heat controller to the variable rate solenoid on gas
control valve.

— Line voltage is sent to transformer and to ignition

control.

— 24 V.A.C. is sent from transformer to the ignition

control.

— Red light on ignition control is illuminated
— Ignition control module performs an internal safe start

check
-- Internal components are tested
-- Amperage is sent to flame sensor from ignition

control to start flame proving process.

-- Ignition control terminal PSI sends 24 volts to air

proving switch.

— Ignition control module begins safety lockout timing
— Ignition control module sends 115 volts from terminal

IND to the fan motor.
-- Fan motor starts
-- Air proving switch closes and 24 volts is returned

to ignition control terminal PSO.

— Fan motor stops.
— Ignition control 115 volts from terminal HSI to the

igniter.
-- Ignitior heats up in 17 seconds.

— Ignition control restarts the fan motor.
— Air proving circuit is rechecked.
— Ignition control sends 24 volts from terminal MV to the

gas control valve through the high limit switch.

— Ignition occurs.

-- Ignitor stays powered for 6 seconds until flame

proving occurs.

— Ignition control shuts the ignitor down.

-- Gas valve stays open

— Room warms to desired temperature

-- Room sensor is satisfied
-- Heater shuts down

— Process begins again on call for heat

MULTIPLE IGNITION TRIAL SEQUENCE:

— First trial for ignition takes approximately 45 seconds
— Two more trials for ignition will occur

-- Second trial follows immediately if first trial fails
-- Module starts a 15 minute wait period to allow

ignition Interruption to pass

-- Third and final trial occurs after 15 minute wait

period

— If ignition control module does not prove flame after

third trial, the module goes into safety lockout (3 Flash
Pattern)
-- Igniter shuts down
-- Fan motor stops
-- Gas valve closes

— Ignition control must be reset

-- Unplug the heater and plug it back in

-- OR --

-- Turn building controller off and then back on to call

for heat