PRePaRaTIon of sITe anD foUnDaTIon

1. General

Before the Mueller prefabricated steel building arrives, the site and foundation should be prepared .
This includes leveling the terrain and constructing the foundation . Mueller buildings are typically
designed to be placed on a permanent slab . A concrete contractor is highly recommended for this
phase of the construction .

2. Procedural steps

A . Remove trees, debris, and other items from the building location .

B . Smooth and level the ground where the foundation is to be made .

C . Construct the foundation using the materials recommended by your concrete contractor .

noTe: Mueller steel building systems will provide blueprints that show placement in

the concrete slab. check the anchor bolt plan thoroughly upon receipt. If you

have any questions, call your Mueller steel building systems salesperson.