- 10 -
Updating Date and Time In the Meter
The Soil Compaction Supervisor has an internal clock that
supplies the date and time for the data records. The internal
clock can be updated as required using a setup key. The
update process requires steps to be performed using the
key reader and the Soil Compaction Supervisor. Have both
available before starting the procedure.
Key Reader-
1.
Make sure the date and time are correct on the
computer.
Note: The date and time from your computer will be
written to the setup key when it is created.
2.
Start the MBW Key Reader program (if it is not
already running).
3.
Insert the key into the reader. The status of the key
will be displayed in the message area.
4.
Press the “Make Setup Key” button.
Note: All data on the key will be erased when creating a
setup key.
5.
Remove the setup key from the reader after it is
created.
Soil Compaction Supervisor 2-
1.
Unplug the sensor from the SCS2 (if one is plugged
in).
2.
Press the power button to turn on the Soil
Compaction supervisor.
3.
Wait for the self test to finish, then insert the setup key
into the Soil Compaction Supervisor.
4.
Press and hold the power button. Release the power
button when the lights on the right side of the unit
blink in unison.
Note: The SCS2 will turn off when the date and time are
updated.
5.
Turn the SCS2 on with the setup key in place.
Note: This will turn the setup key into a data key.
Machine Type
Completion status
Description
Percussion
Competed Normally
Normal results using a percussion compactor.
Vibratory
Completed Normally
Normal results using a vibratory compactor
Unknown Device
Lost sensor
Sensor was disconnected while monitoring
compaction.
Unknown Device
Inactivity Time-out
Compaction was started, and then stopped
before the STOP light was turned on. The
meter then automatically powered off after 10
minutes.