SECTION 4 - MACHINE OPERATION

4-6

– JLG Lift –

3121211

Outrigger Installation

(See Figure 4-5. on page 4-7)

NOTICE

AS A SAFETY PRECAUTION, DUE TO DIFFERENT LENGTHS, OUTRIGGER BEAMS
ARE DESIGNED TO FIT A SPECIFIC MODEL AND ARE NOT INTERCHANGEABLE.

1. Remove one outrigger beam from the stowage socket.

2. Insert outrigger beam into an outrigger socket on the

base frame with outrigger interlock contact on the
bottom. Push outrigger beam in socket until locking
pin on side of outrigger socket snaps into the outrig-
ger beam detent. Repeat for remaining outriggers.

3. With all outriggers inserted, turn each outrigger jack

down, lifting entire machine until all wheels are off the
ground.

4. When all four (4) wheels are off the ground, use the

bubble level on the base frame to level machine.

NOTICE

MACHINE WILL OPERATE ONLY IF ALL FOUR (4) INTERLOCK LED LIGHTS ARE
ILLUMINATED.