Platform installation, 6 machine shut down and park, Platform installation -10 – JLG 41AM Operator Manual User Manual

Page 54: Machine shut down and park -10

Advertising
background image

SECTION 4 - MACHINE OPERATION

4-10

– JLG Lift –

3121211

Platform Installation

1. Using two people or suitable lifting equipment, lift

platform and set platform upper support rail into the
upper platform mount on the mast.

2. Swing platform lower support rail into lower platform

mount on the mast.

3. Secure platform support rails with two (2) platform

upper mount pins, and two (2) lower platform mount
pins.

4.6

MACHINE SHUT DOWN AND PARK

1. Ensure platform is fully lowered, turn key switch to

OFF position.

2. Store outrigger beams in stowage sockets.

3. Move machine to a well-protected and well-ventilated

area. In a hostile environment, cover machine for pro-
tection.

4. Apply caster brakes and chock at least two wheels

when parking machine for extended time.

5. Remove key switch to disable machine from unau-

thorized use.