SECTION 2 - SERVICE PROCEDURES

3120775

– JLG Lift –

2-31

one side or the other.
The threaded end of the chain/cable may need to be
restrained while tightening the adjust nut to keep the
chain/cable from twisting.

7.

Retract the mast all the way and check if the top of
the mast sections appear as shown in Figure 2-6.

8.

Repeat steps (1) through (7) for remaining mast sec-
tions.

9.

Once mast section adjustment is completed, apply
loctite #242 to the threads under the (jam) nuts that

were loosened. Then re-tighten the loosened (jam)
nuts until tight against the top (adjust) nut. Chain/
cable should have slight tension but should not be
taut.

10.

After all mast adjustments are complete, if neces-
sary adjust the bumpers on the underside of the
stock-picker platform so the platform rests slightly
above the base frame when it is lowered and empty.

Figure 2-6. Mast Chain/Cable/Sequence Cable Adjustment Components. (Typical)

SECTION-1

FIXED

TO BASE

SEQUENCE CABLE

ADJUST NUT

CHECK IF OVERALL HEIGHT

OF MACHINE FROM

FLOOR TO TOP OF MAST

IS WITHIN SPECIFICATION

SECTION-2

EXTENDED BY

CYLINDER

SECTION-5

(PLATFORM

HEADER SECTION)

EXTENDED BY

CHAIN/CABLE

CHAIN/CABLE

ANCHOR PLATE

ADJUST NUT

JAM NUT

THREADED

CHAIN/CABLE

END

SECTION-4

EXTENDED BY

CHAIN/CABLE

SECTION-3

EXTENDED BY

CHAIN

STEP APPROXIMATELY

1/4 in. (7mm)

MAST SIDE PROFILE

MAST CHAIN/CABLE ADJUSTERS

Note: When

pply Loctite #242 to the

threads under the jam nut.

.

chain adjustment

is complete, before

tightening the jam nut

against the adjust nut,

a

Advertising