Mast section 3 removal (all masts), Mast section 2 removal (all masts), Mast section 1 disassembly (all masts) – JLG 41AM (3120752) Service Manual User Manual

Page 47

Advertising
background image

SECTION 2 - SERVICE PROCEDURES

3120752

– JLG Lift –

2-23

22. Carefully slide mast section-4 out BOTTOM of sec-

tion-3. Remove slide pads, shims and chain anchor
plate, if necessary.

Mast Section 3 Removal

(All Masts)

23. Remove chain adjust nuts from threaded ends of

chain attached to the chain anchor plate on BOT-
TOM end of mast section-3. Push threaded ends of
cable through anchor plate.

24. At TOP of mast section-3, pull chains out and allow

to hang loose, (be certain floor surface is clean and
free of any metal chips or debris which may stick to
lubricated chains or lay chains in a clean bucket)
.

25. Slide mast section-3 out TOP of mast section-2 far

enough to allow access to the chain sheave wheel
assembly.

26. Remove countersunk flathead screws securing

chain sheave wheel assembly attach bars on both
side rails at TOP of mast section-3 and remove
sheave wheel assembly.

27. While mast section-3 is still extended from section-2

remove the bolts attaching the two (2) chain assem-
bly anchor blocks to the TOP of mast section-3.
Remove chains.

NOTE: When sliding mast sections apart, be careful not to

scratch or score the anodized finish in the slide pad
channels.

28. Carefully slide mast section-3 out BOTTOM of sec-

tion-2. Remove slide pads, shims and chain anchor
plate, if necessary.

Mast Section 2 Removal

(All Masts)

29. Slide mast section-2 out TOP of mast section-1 far

enough to allow access to the chain anchor block/
sheave wheel assembly.

30. Remove countersunk-flathead screws securing

chain anchor block/sheave wheel assembly attach
bars on both side rails at TOP of mast section-2.

31. Extend the chain anchor block/sheave wheel

assemby and hydraulic cylinder rod out the TOP of
mast section-2 far enough to allow removal of the
sheave wheel attach bars, sheave wheels and
sheave pin from the chain assembly anchor block.

32. Remove the setscrew holding the hydraulic cylinder

rod into the chain assembly anchor block. Lay chain
assembly to side.

NOTE: When sliding mast sections apart, be careful not to

scratch or score the anodized finish in the slide pad
channels.

33. Carefully slide mast section-2 out the TOP of sec-

tion-1, be careful not to nick or score cylinder rod
surface while removing. Remove slide pads and
shims, if necessary.

Mast Section 1 Disassembly

(All Masts)

34. Slide the TOP of the remaining mast section-1 out

over edge of work surface and remove the bolts
attaching the anchor blocks of the two (2) chain
assemblies to mast section-1. Remove chain assem-
blies from mast and lay aside.

35. Remove the hydraulic lift cylinder from it’s mount

attached to mast section-1, if necessary.

36. Remove slide pads and shims from mast section-1,

is necessary.

Mast disassembly should now be complete.