Commissioning, Operating instructions safety system ces-az-aes, Led indicators – EUCHNER CES-AZ-AES-xxx (Unicode) User Manual
Page 14: Teach-in operation
 
Operating Instructions Safety System CES-AZ-AES-...
14
Commissioning
LED indicators
STATE LED
green
State display (multifunction display using flashing modes)
OUT
LED yellow
Safety circuit closed
DIA
LED red
- Operating error or
- External fault (fault in the feedback loop) or
- Teach-in process not valid or
- Internal device fault or
- TST input activated (function test active)
Teach-in operation
Before the system forms a function unit, the parameters are set in the evaluation 
unit in a teach-in operation (number of connected read heads, assignment of 
the actuators to the read heads, with or without automatic start, with or without 
feedback loop). In this process, the read heads are activated and the actuator 
code is learned.
These configuration parameters are saved in the non-volatile memory in the evalu-
ation unit.
The safety outputs are open during the teach-in operation. The system is in a safe 
state.
Important!
Ì
During the teach-in operation the following conditions must be met:
Ì
There must be no state change, e.g. opening a safety guard or closing a 
further safety guard or a change in the signal on the terminals for the start 
button and the feedback circuit.
Ì
The power supply must not be switched off.
Ì
If these conditions are not met, the evaluation unit switches to the safe fault 
state (diagnostics LED illuminates) and signals this operating fault with the 
STATE LED by 3 short flashes that are repeated every second. The teach-in 
operation must be repeated.
Ì
The number of teach-in operations is unlimited. The evaluation unit can be 
re-configured as often as required.
Ì
Actuators cannot be interchanged without a renewed teach-in operation.
Ì
An actuator that has not been subjected to teach-in will not be detected by 
the related read head.
Ì
Even if only one new actuator needs to be taught, a complete new teach-in 
operation must be carried out as described in the section Setup.
Ì
Do not change DIP switches during operation.
To trigger a teach-in operation, the user must perform the following actions in the 
stipulated order:
1. Prepare for teach-in operation
Ì
Switch off power supply U
B
Ì
 Fit a jumper between terminals J1 and J2 
 (for CES-AZ-AES-01B between J and 0V)