Figure 3: Installation - Chimney

Figure 4: Installation - Skylight

1-800-241-4402 www.green-guard.com

GreenGuard

®

Synthetic Roofing Underlayment Installation Guide

6. Installation – Chimney, Skylight, and Vent/Pipe Penetrations

A.

All applicable building and fire codes shall be followed with respect to placement of roof underlayments near heat

producing vents or chimneys.

7. Installation – Valley and Ridge Areas

A.

A single 24 inch wide layer of roof underlayment shall be installed and centered vertically at all valley, hip and ridge

areas prior to installation of the underlayment in the field or main area of the roof.

B.

Self-adhering flashing around protrusions or metal drip edges shall be installed over the roof underlayment to allow

for proper drainage and to prevent water backup. In valley locations, the valley self-adhering flashing shall overlap

the field roof underlayment.

C.

The GreenGuard® Synthetic Roofing Underlayment shall be covered with the final roof covering as soon as possible

as it is not designed for prolonged outdoor exposure (maximum 6 months). The final roof covering shall be installed

in accordance with the manufacturer’s installation instructions.

Figure 5: Installation - Roof Valley