4 • 65-2394RK Combustible Gas Transmitter

Test Points

The test points are on the left side of the amplifier (see Figure 1). The test points produce a
100 mV to 500 mV output that corresponds to the transmitter’s 4 to 20 mA output. Use the
test points and a voltmeter to measure the amplifier’s output during the start-up and
calibration procedures. The black test point in the lower left corner is the negative (-) test
point and the red test point below the zero pot is the positive (+) test point.

Junction Box

Use the junction box to install the transmitter at a mounting site that is remote from the
controller. The junction box protects the amplifier and wiring connections made to the
amplifier. Use the top 3/4’’ conduit hub to connect wiring from the amplifier to the
controller. Use the cover on the front of the junction box to access the interior of the
junction box. The detector and amplifier are factory installed in the junction box. Three
spacers installed on the back of the junction box control the distance of the junction box
from a mounting surface and ensure that there is enough room to install a calibration cup
on the detector during calibration.

Installation

This section describes procedures to mount the combustible gas transmitter in the
monitoring environment and wire the transmitter to a controller.

Mounting the Combustible Gas Transmitter

1.

Select a mounting site that is representative of the monitoring environment. Consider
the following when you select the mounting site.

Select a site where the transmitter is not likely to be bumped or disturbed. Make
sure there is sufficient room to perform start-up, maintenance, and calibration
procedures.

Select a site where the target gas is likely to be found first. For lighter gases,
mount the detector near the ceiling; for heavier gases, mount the detector near the
floor.