Dig the hole for the concrete footing, and prepare the concrete. You

will need approximately 4-1/2 cubic feet. The top surface of the

footing should be about 12” by 18” and extend 36” into the ground.

See the illustration for the relative position of the rectangular footing
to the post and mailbox. The bottom of the hole for the concrete

footing should be filled with about 6” of gravel to promote drainage

under the post. The top of the footing should be sloped for water

runoff.

The concrete must be below the frost line. Otherwise the post will

move when the ground freezes. Be careful not to puncture water,

sewer, or gas lines when digging holes for footing.

Four (4) 1/2”-13 by 8” long J-shaped anchor bolts and eight (8) 1/2”-
13 nuts are provided. Attach the anchor bolts to the base of the post

with four (4) nuts under and four (4) nuts over the bottom mounting

plate. Pour the concrete into the hole, prodding the mix with a stick

while filling to reduce any air pockets. Press the anchor bolts on the
bottom of the post into the concrete until the bottom plate is resting

on the top surface of the wet concrete. Use a carpenter’s level on

the sides of the post to ensure that the post is aligned vertically.

Periodically check the vertical alignment of the post as the concrete
is curing.

The concrete will shrink as it hardens, leaving a space between the

anchor and the concrete when it is cured. To prevent this, loosen the

top bolt one full turn prior to inserting into the wet concrete. After the
anchor is inserted into the wet concrete, place your foot on the top of

the threaded anchor and push down until the top nut is pressed

against the anchor plate. After the concrete has hardened, re-tighten

the top bolt.





SALSBURY INDUSTRIES

1010 East 62

nd

Street, Los Angeles, CA 90001-1598

Phone: 1-800-624-5269 Int’l Phone: 323-846-6700

Fax: 1-800-624-5299 Int’l Fax: 323-846-6800

www.mailboxes.com engineering

@

mailboxes.com

Installation instructions are provided as general guidelines. It is advised that a professional installer be consulted. Salsbury Industries assumes no product assembly or installation liability.

Copyright © 2010 Salsbury Industries. All rights reserved. (Rev. 03, 10/27/2010) Page 4 of 5

Advertising