12. Set the foldplates to the proper open and closed
positions by rotating the stop blocks and placing 
the correct symbol for either open of closed to 
the position closest to the fold rollers. Then set 
the desired fold depths using the scale on the belt 
and reading at the yellow mark on the indicator. 
13. Setup the slittershafts using the proper
perforating scoring or slitting accessories. If just 
a parallel folder is being used an perforating, 
scoring or slitting is not required, pullout tires 
must still remain on the slittershafts to properly 
eject the sheets. Note that a good setup procedure 
is to have all the setscrews facing outward at the 
same clock position. This eliminates a lot of 
handwheel turning to get to the setscrews during 
job changes. See Fig. 7 
14. Setup Delivery Stacker Wheels to the expected
position of the paper as it ejects the folder. The 
independent speed control will need to be set 
during the initial fold operation to insure proper 
shingling. Note that the exit holddown straps 
must also be installed to kick the sheet down 
onto the delivery stacker. 
 
 
Right angle Folding
 
When adding an 8-page or 16-page folder to a 
parallel unit it is highly recommended that the stock 
must be either perforated or scored as it exits the 
previous fold unit. The perforating or scoring is to be 
performed at the line of the fold that is to be folded in 
the next fold section. This weakens the grain of the 
stock so that a consistent, quality fold can be 
achieved. Perforating is also needed to relieve air that 
can become trapped in the folding process and create 
wrinkles in the paper. The size of the perforator tooth 
can make a difference in the amount of air that can 
escape and remove the wrinkle problem. Failure to 
score or perforate a sheet going into a right angle 
folder will result in inconsistent fold quality. 
 
 
Refer to your operator’s manual for scoring, 
perforating and slitting information. 
 
Marbleholder Setup 
Note that marble placement can be critical on some 
jobs and not on others. You may want to remove 
some marbles that are in the end that accepts the 
sheets at a right angle so that the sheets do not 
bounce back when trying to get under the marbles. At 
least (2) steel marbles are recommended at the end 
closest to the fold rollers to maintain sheet control 
against the guide. 
Fig. 7 Perforating on 1-1/8” slittershaft 
 
 
 
Scoring with 1-1/8” slittershafts 
 
 
 Scoring on a 7/8” slittershaft 
 
Perforating on a 7/8” Slittershaft