Kenco Engineering Pneumatic Float Switch User Manual

Kenco engineering company

Advertising
background image

KENCO ENGINEERING COMPANY

P.O. BOX 470426, TULSA, OK 74147-0426

PHONE: (918) 663-4406 FAX: (918) 663-4480

http://www.kenco-eng.com

e-mail:

[email protected]


INSTALLATION & OPERATIONS MANUAL

FOR PNEUMATIC FLOAT SWITCHES

MODEL 106:
The Pneumatic Float Switch is installed in a 2" half coupling which is welded into the
tank wall. Be certain that the hole in the tank wall is at least as large as the inside
diameter of the half coupling, so there is no interference with the 106 float arm action.
The float will operate in a fluid specific gravity of 1.00 or greater.

MODEL 207:
The 207 water make-up valve is installed by connecting the 207 housing to the expansion
tank. A bracket should be made to support the 207. The centerline of the housing should
be located 3/4" or 1 3/8" above the desired trip point.

HIGH LEVEL SWITCH:
To release the pneumatic line pressure when the liquid level reaches the high level of a
tank, connect the pneumatic line to inlet port "B" and plug port "C". The switch will
release the pneumatic pressure when the liquid rises.

LOW LEVEL SWITCH:
To release the pneumatic line pressure when the liquid level reaches the low level of a
tank, connect the pneumatic line to inlet port "C" and plug port "B". The Switch will
release the pneumatic pressure when the liquid level falls.

SWITCH TRIP POINTS:
The 1 3/8" dimension shown below will be below the switch centerline if switch or entire
assembly is rotated 180 degrees. Trip point dimensions are based on tests with water at
ambient temperature. Trip points may vary with liquids other than water.










Advertising