8. Install vapor elbow (see Fig. 5B) with equalizer adapter to

suction tube of line set and suction connection to indoor coil.
Adapter has a 1/4-in. male connector or attaching equalizer
tube.

9. Connect equalizer tube of TXV to 1/4-in. equalizer fitting on

vapor line adapter.

10. Attach TXV bulb to horizontal section of suction line using

bulb straps provided. (See Fig. 5C.) Insulate bulb with
factory-supplied insulation tape. (See Fig. 5E.) See Fig. 6 for
correct positioning of sensing bulb.

11. Proceed with remainder of unit installation.

FAN COIL

To obtain efficiency rating for 38TDB037 with FV4ANB006
fancoil TXV must be replaced with factory supplied TXV.

Replacing R-22 TXV or Non-Balance Port Puron TXV

1. Remove any existing refrigerant and ensure coil has not been

exposed to atmospheric pressure for more than 15 minutes.

2. Remove coil access panel and fitting panel from front of

cabinet.

3. Remove and save TXV support clamp using the 5/16-in. nut

driver. Save the clamp.

4. Remove TXV using a backup wrench on flare connections to

prevent damage to tubing.

5. Using wire cutters, cut equalizer tube off flush with vapor tube

inside cabinet.

6. Remove bulb from vapor tube inside cabinet.

7. Braze equalizer stub-tube closed. Use protective barrier as

necessary to prevent damage to drain pan.

IMPORTANT:

Route the equalizer tube of the approved Puron®

TXV through suction line connection opening in fitting door prior
to replacing fitting panel around tubing.

8. Install TXV (Fig. 5A) with 3/8-in. copper tubing through

small hole in service panel. Use wrench and backup wrench,
to avoid damage to tubing valve.

9. Reinstall TXV support clamp (removed in item 3).

10. Attach TXV bulb to vapor tube inside cabinet, in same

location as original was when removed, using supplied bulb
straps. (See Fig. 5C.) See Fig. 6 for correct positioning of
sensing bulb. Insulate bulb with factory-supplied insulation
tape. (See Fig. 5E.)

11. Route equalizer tube through suction connection opening

(large hole) in fitting panel and install fitting panel in place.

12. Sweat inlet of TXV, marked “IN” to liquid line. Avoid

excessive heat which could damage valve.

13. Install vapor elbow (see Fig. 5B) with equalizer adapter to

vapor line of line set and vapor connection to indoor coil.
Adapter has a 1/4-in. male connector for attaching equalizer
tube. (See Fig. 5B.)

14. Connect equalizer tube of TXV by 1/4-in. equalizer fitting, on

vapor line adapter. Use backup wrench to prevent damage to
equalizer fitting.

15. Proceed with the remainder of unit installation.

LONG-LINE APPLICATIONS

For refrigerant piping arrangements with equivalent lengths
greater than 50 ft or when elevation difference between indoor
and/or outdoor unit is more than 20 ft, follow all requirements of
the Long-Line Guideline section in the Application Guideline and
Service Manual—Air Conditioners and Heat Pumps Using Pu-
ron® Refrigerant.

Step 6—Make Piping Connections

Relieve pressure and recover all refrigerant before system
repair or final unit disposal to avoid personal injury or death.
Use all service ports and open all flow-control devices,
including solenoid valves.

Fig. 4—TXV Installed

A91277

THERMOSTATIC
EXPANSION
VALVE

EQUALIZER
TUBE

SENSING
BULB

COIL

Fig. 5—TXV Kit Contents

A01418

A

B

D

INLET

COIL

E

BULB

INSULATION

TAPE

C

Fig. 6—Positioning of Sensing Bulb

A00399

SENSING BULB

STRAP

8 O'CLOCK

4 O'CLOCK

3