Floating Installation Procedure

Step 1 - Pre-install Activities

•

Rack up planks from several boxes.

•

Ensure that end joints are staggered at least 6” between the rows. See diagram below.

•

Inspect product for defects. If material is questionable, contact the retailer immediately. Do not proceed with installation


Step 2 – Install Moisture Barrier (if on concrete) and Optional Underlayment if selected.

•

For concrete, let the moisture barrier run up the wall a bit before cutting to size.

•

Install the underlayment on top of the moisture barrier. Cut 1 inch from the wall. See diagrams below.


Step3 – Install the First Row

•

Saw off the tongue from the length and width of the first plank. Create expansion gap by placing spacers be-tween the planks and
the walls for expansion.

•

Saw off the tongues from only the length of the remaining planks to be installedin the first row..

•

Use the angling method to connect and lock the joints between the planks. Remember to use the spacer for maintaining expansion
gap. See diagrams below.


Step 4 – Install the Remaining Rows

•

Stagger the end joints by at least 6 inches. Use angling method to lock the joint along the long edge.

•

Use the angling technique to lock the long edge together.

•

Use either the tapping block or pull bar to drive the next plank toward the first plank until the end joints are locked.

•

Repeat the steps until the row is complete. See diagrams below.