2 BGN891 Direct Spark Ignition Control Installation Instructions

Table 1: Normal Operating LED Indications

Green LED

Definition

Rapid Blinking

Spark Active

Steady On

Flame Detected, Main Burner On

0.5 Second On/Off

Pre-purge, Interpurge or Post-
purge

0.5 Second On
4.5 seconds Off

Retry or Recycle Time

Table 2: Error Code LED Indications
Error Codes Blink 0.25 Second On/Off
then Pause 1.0 Second and Repeat.

Led Light

Error Definition

Error

Type

Blinks 1 Time

No Flame in Trial Time

Lockout

Blinks 2 Times

Flame Sense Circuit

Lockout

Blinks 3 Times

Pilot/Main Valve Circuit

Lockout

Blinks 4 Times

Flame Loss

Lockout

Blinks 7 Times

Ground or Internal

Lockout

Steady On

Line Voltage/Frequency

Standby


RES100A-600 Resistor Installation
Instructions

Application

The RES100A-600 Resistor is a direct replacement
for Honeywell 202764BAC Resistor and is used in
certain applications to ensure compatibility with
power-stealing thermostats. The RES100A-600 is a
1000 ohm, 3 watt resistor.

Installation

When Installing this Product…

IMPORTANT:

Only qualified personnel

should install or service BASO Gas Products®.
These instructions are a guide for such personnel.
Carefully follow all instructions for the appliance.

!

CAUTION: Electrical Hazard.

Can Cause Electrical Shock or Equipment
Damage.

Disconnect power supply before installing resistor.

To Install the Resistor

1. Loosen terminal screws as shown in the

application drawing.

2. Slide the resistor leads under the terminal

screws and tighten the screws.

3. Turn on the system power.
4. After installation is complete, check out product

operation as provided in these instructions.

R

W

1

2

3

L1
(HOT)

L2

TACO ZONE VALVE

RESISTOR

1

2

1

2

POWER SUPPLY PROVIDES DISCONNECT MEANS AND
OVERLOAD PROTECTION AS REQUIRED.

BEND RESISTOR AWAY FROM ZONE VALVE CASE
TO PREVENT SHORTING.

Figure 2: Connect Resistor to Taco Zone Valve Terminals 1 and 2

DISCONNECT POWER SUPPLY BEFORE INSTALLATION

1

Figure 1: Connect Resistor to ST9141 Fan Timer Terminals C and W

C

G

Y

W

R

ST9120A-G

1

Note: If furnace fails to start, remove flapper and clean before re-starting.