Jaypro Sports BBFP-20 User Manual
Page 5

9/5/12
Page 5 of 5
Foul Pole Assembly:
1. Install the yellow powder coated cap on top of foul pole with #12-14 self-
drilling screw.
2. Install one anti-rotation rod into the bottom side of the lower foul pole. By
inserting it into the pre-drilled hole with 1/2" flange nuts back to back as
shown in the illustration below.
3. Pour concrete into the footing and reinforce with six 3/4” x 36” long rebar
(consult local building code. Rebar not included, to be provided by
installer) evenly space around the spot for the lower foul pole.
4. Using a lifting device (crane) place the foul pole into the footing and fully
support it in a plumbed position.
5. Slop the top of the footing for drainage if desired. Wait for concrete to
fully cure (approx. 48 hours).