Figure 28: Valve Cable Connections
17. Connect the CAN Node cable (C02B)
to the 4-pin AMP plug on C11 (Figure
29).
18. Route the CAN Node cable (C02B) to
the roll sensors which are installed in
Section 4.5. Follow existing cables
and/or hydraulic lines.
19. Connect the 4-pin AMP connectors to
the roll sensors.
20. Connect the sensor branch cable (C02)
to the 4-pin AMP plug on C02B
(Figure 29).
21. Route the sensor branch cable (C02) to
the wing and main sensors and connect
to the sensors. Follow existing cables
and/or hydraulic lines along the boom.
22. Cable-tie the installed cables every 12
inches.
IMPORTANT:
Provide enough slack in all cables to
account for the movement of the
main section, parallel lift, and
FOLDING boom movement.