3 hydraulic installation, 1 valve mounting – NORAC UC4+BC+FT2A User Manual
Page 13

9
4.3 H
YDRAULIC
I
NSTALLATION
4.3.1 Valve Mounting
1. On a clean surface remove all plastic
plugs from the NORAC hydraulic Valve
(V01) (Figure 9).
Figure 9: NORAC Valve Block
2. Install the orifices (F06) into the “B”
ports with the notch facing outward
as shown in Figure 10.
Figure 10: Valve Block Assembly
3. Install the 6MB-6MJ fittings (F04) into
the “B” ports and tighten to 18 ft-lbs.
4. Install the 6MB-plugs (F05) into the “A”
ports and tighten to 18 ft-lbs.
5. Insert the 0.047” orifice (F06) into the
“A” port of the 3
rd
station of the block
with the notch facing in (Figure 10).
6. Insert the 0.042” orifice (F07) into the
“B” port of the 3
rd
station of the block
with the notch facing in (Figure 10).
7. Mount the 6MB-4MOR fittings (F04)
into the “A” and “B” ports on the
NORAC 3
rd
station portion of the
block.
8. Mount the NORAC valve (V01) to the
sprayer in a suitable location.