5 completing the factory installation – NORAC UC4+BC+HD8A User Manual

Page 24

Advertising
background image

21

5

COMPLETING THE FACTORY INSTALLATION

1. Test the functionality of the original

manufacturer’s boom controls. Power to
the NORAC control panel does not need to
on be for the sprayer controls to function.
Unfold the booms and raise/lower each
boom and main section. If one or more of
these functions do not work, review the
hydraulic and electrical portions of this
manual to check for proper installation.

2. Confirm that the cabling/hoses are at

agreeable lengths for the entire range of
motion.

3. Prepare the spray boom for the software

installation.

 Unfold the booms and level to 90 cm (or

35 inch) nozzle height. Ensure the boom
slant is in its centered position.

 At this point ensure the UC4+ sensors

are reading from an adequate and
uniform target, such as gravel or dirt.
Do not attempt to perform the

installation over grass or crop.

 If the installation is done over concrete,

place carpet beneath the sensors to
avoid sensor problems during the

installation.

4. Switch on the UC4+ control panel and find

the HD8 sprayer type by toggling through
the sprayer list using the +/- switch. At this
point two install options are available:

a) Complete Install- this will setup the

entire Autoheight system, requiring fully
range of boom moment. Hydraulics will
be calibrated to the hydraulic power unit
connected. To perform a complete
install press “Yes” and follow the on
screen instructions.

b) Quick Install- this will require the boom

to be unfolded at 90cm spray height but
no hydraulic movement will occur
(hydraulic calibration will occur at a later
time by performing a “Retune” on the
final hydraulic power unit. To perform a
Quick Install, press and hold the “Yes”
switch until “SENSOR” appears on the
screen and release. Follow the on screen
instructions.

4. For more information on performing the

software setup and calibration refer to the
UC4+ Operators Manual.

Advertising