Swath Manager 5 Functions

•

Auto control up to five boom sections.

•

The CenterLine determines when sections are in or out of an applied region.

•

The Rate Controller maintains full control over product application.

•

Boom Sections are activated and deactivated based on the percentage of boom
overlap setting (0%, 50%, 100%).

Installation

Cable 45-05462 & 45-05463

•

Connect between controller and main harness

Cable 45-05467

•

Use T-Taps supplied with harness to tap into the signal wire between switchbox or
existing switches and boom shutoff valves.

Figure 1: %Overlap Examples

Figure 2: Installation System Diagrams

0%

50%

100%

SM5 Controller Harness

TeeJet - 45-05462

Raven - 45-05463

Existing

Controller Harness

MASTER

5

4

3

2

1

BOOM CONTROL

AUTO
BOOM

DISENGAGE

ENGAGE

Swath Manager 5

Automated Boom
Section Control

844-x

SPR

AYER C

ONTROL

ON

P

RO

AUTO

MAN

ON

OFF

Rate Controller

Valves

IGN Sense

CenterLine

Status Detect

(Not used)

Power

Cable

45-05324

GPS IN

Cable

SM5 to CenterLine

45-05461

Not Used

Swath Manager 5

78-08065

SM5 Harness,

Exsisting Switches or Switchbox

45-05467

To Accessory Power

or Battery

Existing switches or switchbox

Swath Manager 5

78-08065

IGN Sense

CenterLine

Status Detect

(Not used)

Power

Cable

45-05324

GPS IN

Cable

SM5 to CenterLine

45-05461

Not Used

Valves

MASTER

5

4

3

2

1

BOOM CONTROL

AUTO
BOOM

DISENGAGE

ENGAGE

Swath Manager 5

Automated Boom
Section Control

Wire Splice