INSTALLATION INFORMATION

~ 10 ~

1. Pier spacing must be in accordance with the Home Manufacturer’s
Installation Manual and/or State or Local requirements.
2. Clear all vegetation and debris from the area where the ABS pads
are to be placed.
3. Ground under ABS pads must be leveled and evenly compacted.
4. Place ABS pad with grid side up, smooth side down. Center
blocks on ABS pad and complete pier.

Installation Instructions for ABS Pads

Pad Bearing Capacity

ABS Pad

Part#

1000 lbs.

2000 lbs.

3000 lbs.

Size

Soil

Soil

Soil

16" x 18"-

2 Sq. Ft

59300

2,000 lbs.

4,000 lbs.

6,000 lbs.

288 Sq. In.

16" x 22.5" -

2.5 Sq. Ft. 59301

2,500 lbs.

5,000 lbs.

7,500 lbs.

360 Sq. In.

17" x 25"-

3 Sq. Ft

59302

3,000 lbs.

6,000 lbs.

N/A

432 Sq. In.

24" x 24" -

4 Sq. Ft

59303

4,000 lbs.

8,000 lbs.

N/A

576 Sq. In.

Ground Level

ABS Pad

Concrete

Block

Ground Level

ABS Pad

Concrete

Block

RIGHT

WRONG

Unlevel or poorly compacted soil

Ground Level

ABS Pad

Concrete

Block

Max. 1/8”
Deflection

Deflection is measured from the highest point to the

lowest point of the top side of the pad.

Adjustable Outrigger/Diagonal Strut

Installation Instructions

1. Determine floor joist area needing support.
2. Set mounting plate on floor joist and secure with 5 (#12x2”)

screws provided. Approx. 6” from outer rim joist.

3. Insert threaded bolt in support tube and adjust so it clears

I-beam flange when mounting plate is inserted and chisel end of

bolt is placed against the frame. If support tube is too long,

simply cut square to desired length.

4. Raise floor joist with jack to desired level before tightening the

nut on the threaded bolt, snug fit to 1/4 turn past.

5. Replaces perimeter piers required for window and door support

and alignment, except as required by the home manufacturer for

larger openings.

6. For manufactured homes only, built to Federal Manufactured

Home Construction & Safety Standards.

7. The total allowable load is 864 pounds, (liveload 665 pounds),

which is the load at each side of a 46-1/2” sidewall opening in a

30 PSF roof zone for a roof tributary of 8’-6” (e.g. a 180” unit

width a 12’ eaves).

Floor Jois

t

Top Floo

r

Botto

m Flo

or

Adjustment

Locking Nut

Threaded

Bolt

6"

I-Beam

Screws

(5)

Mounting

Plate

Support

Tube

Adjustment/Locking

Nut

Threaded Bolt

Do not use on homes while being transported.

NOTE: This component is not designed or intended to replace any foundation supports required by the

home’s manufacturer and is not a repair for damaged joists.