Twin City Fan & Blower IM-3100

Maintenance

General

Fan shaft bearings on belt drive units are factory lubri-

cated and require no lubrication for the first 3-6 months

of operation. Lubricate at intervals shown in Table 3

thereafter. With fan running and with a low pressure

grease gun, add grease slowly until a slight bead forms

between the seals. Use Sinclair Litholene, Shell Gadus

S2 V100 2, Socony Vacuum Armvac 781, Sinclair Oil

Stranolith 57 or equal.

Belts on belt-drive units should be readjusted after 24

hours of operation. Loosen motor base bolts and apply

15 lbs. pull per belt for proper belt tensions. Tighten

motor base bolts.
Check contact surfaces of belt for excessive wear. If

belts have a slick, glazed look or are cracked, belts are

slipping. Replace belts as required.
Motors require no lubrication for 10 years of normal

operation.
The inlet venturi is molded shock-resistant, bonded,

reinforced fiberglass and will require no maintenance.

Wall Application

1. Servicing or inspecting the unit can be accomplished

from the exterior by removing the flanged extruded

louver and from the interior of the building by remov-

ing the fiberglass inlet (see Figure 2).

2. To remove the motor assembly for servicing, unplug

the motor from the provided outlet and unfasten the

four vibro-isolator bolts. The entire motor assembly,

including the wheel and bearing (belt drive units), will

slide out of the housing.

Inline Application

For easy maintenance of the inlet unit, provide a drop-

out section between the ductwork and duct adapter (see

Figure 3).
Servicing or inspection can then be accomplished by

removing the dropout section, then removing the fiber-

glass inlet. The motor assembly can then be removed

by disconnecting the motor from the provided outlet and

unfastening the four vibro-isolator bolts. Periodic inspec-

tion and cleaning of the fan will insure smooth operation.

Figure 1. Removal of Wood Shipping Supports

Housing

Instructions: Remove wood shipping supports

frame before installing unit

.

3. On three-phase units check and calculate phase unbal-

ance as follows:

% Voltage Unbalance = 100 x max. voltage deviation

from avg. voltage ÷ avg. voltage

Given example: With voltage of 220, 216 and 213
How To Use The Formula:

a. Avg. Voltage = 220 + 216 + 213 = 649 ÷ 3 =

216

b. Max. Voltage Deviation From Avg. Voltage =

220 – 216 = 4

c. % Voltage Unbalance = 100 x (4 ÷ 216) = 1.8%

Voltage unbalance should not exceed 2%.
4. Apply power to unit and check rotation of wheel with

the directional arrow on the unit.

WARNING: Especially check three-phase units for rota-

tion. For three-phase, rotation can be changed by

interchanging any two of the three line leads. If unit is

check on temporary wiring, it should be rechecked

when permanently installed. Motor burn-out or tripped

overload protection devices are usually the result of

wrong rotation.

5.

Electrical Input Check: Perform check of fan ampere

draw and verify that motor nameplate amps are not

exceeded. Take account of the service factory range

if motor is nameplated above a 1.0 service factor.

6.

Fan RPM Check: Fan RPM should be checked and

verified with a tachometer. Refer to Table 2 for maxi-

mum fan RPM values.

WARNING: Running fan at an RPM greater than the

maximum RPM value in Table 2 will overload the fan

motor and lead to premature motor failure.

Table 2. Maximum Fan RPM (Belt Drive Units)

MAXIMUM

MODEL

MOTOR HP

FAN RPM

12HA1B, 2B, 3B

1/4

1740

14HA1B, 2B, 3B

1/4

1470

14HA4B

1/3

1615

14HA5B

1/2

1850

18HA1B, 2B

1/4

945

18HA3B

1/3

1040

18HA4B

1/2

1200

18HA5B

3/4

1365

24HA1B

1/4

575

24HA2B

1/3

633

24HA3B

1/2

725

24HA4B

3/4

830

24HA5B

1

915

30HA1B

1/3

440

30HA2B

1/2

500

30HA3B

3/4

575

30HA4B

1

630

30HA5B

1

1

2

725

30HA6B

2

795

OPERATING CONDITION

GREASING INTERVAL

FAIRLY CLEAN

6 TO 12 MONTHS

MODERATE TO

EXTREMELY DIRTY

1 MONTH

Table 3. Bearing Lubrication Interval

(Belt Drive Model HAB Only)

1.

Frequency or regreasing will vary, depending on the hours of

operation, temperature and surrounding conditions.

2.

Bearings have been prelubricated from factory with NLGI Grade

No. 2 lithium-12 hydroxysterate base grease.