Pre-Installation

Installation

1. Carefully unpack screen.

2. Make sure to recheck measurements of screen

location before installation.

3. Remove center support brackets (on 8' and wider screens only),

reverse brackets and reinstall flush with the top of the box

1. Install screen by raising unit into position between joists at

one end only. Install one lag screw in each mounting bracket.

2. Level unit lengthwise with a carpenter’s level and plumb level.

Secure opposite end.

CAUTION! Do not seal in until screen has been secured in

position and properly tested for satisfactory operation.

ATTENTION! Ne fixez pas l'écran jusqu'à ce qu'il ait été

correctement mis en place et qu'il fonctionne
convenablement.

3. Detach access panel by removing screws, see figure 1.

4. Remove junction box cover plate.

5. Install electrical hook up that applies to your unit. Make sure to

review your electrical installation checklist and wiring diagrams
(included) for either 120 volt switch, 220/240 volt switch or DRC
low voltage control.

NOTE: Must be installed in accordance with the requirements of
the Local Building Codes, the Canadian Electrical Code (CEC), CAN/
CSA C22.1 and the National Electric Code (NEC), NFPA 70.

CAUTION! Do not cut tape on fabric with knife or any sharp
tool. Pull orange string.

ATTENTION! Ne coupez pas le ruban adhésif sur la toile avec

un couteau ou un outil tranchant. Tirez sur le cordon orange.

6. Carefully remove wood boards securing mask surface to case.

7. Carefully remove tape strips securing picture surface around roller.

Slats should move freely (Fig. 2).

8. Test installation by carefully running picture and mask surfaces up

and down several times. Be prepared to stop screen. Standard
Duty Cycle: 1 MIN. ON / 3 MIN. OFF.

9. Run the picture surface upward. When the picture surface is fully

up the limit switch (in the motor) is tripped and the motor shuts off.

10. Test the mask surface the same as testing the picture surface. The

mask will start down off the front of the roller, travel completely
down past the bottom of the viewing surface, then “step back”
against the viewing surface to eliminate shadowing by rolling up
the back side of the roller. Do not adjust the limits to change this
feature.

11. Check for satisfactory condition by operating screen a few times.

Reinstall access panel.

Drywall Screw

Access Panel

Machine Screw

Figure 1

Figure 2

Adjustment

Knob “Up”

Tape Strips

Picture Surface

Slats

Mask Surface

Adjustment

Knob “Down”

Mask Motor

Screen Motor

Advertising