DAMAGE ACTION PROCEDURE FLOWCHART






































Rack is

damaged

Safety officer to assess and classify

the damage

Red Risk

Orange Risk

Green Risk

1. Identify damage for repair.

2. Order materials.

3. Ensure all locations
affected by the damage are
not reloaded after the goods
are removed

Record the extent of
the damage and re-
assess at the next
inspection, but,
within 12 months

Immediately off-load
all affected bays of
racking and repair
damage before re-
use.

The necessary
repairs or
replacement of all
damaged parts are
correctly carried
out.

If repairs are
not carried out
within 4 weeks

Repair carried out

If the severity
of the damage
has increased

If there is no change to
the damage level
continue to monitor at
normal inspection levels
and intervals

Continue in service

Return to service