ULTRA FLAME DIRECT VENT GAS STOVE

14

Direct Vent Kit for Floor Installation

1. Move the stove to its position;

2. Install temporarily an 8 in. section

(4) to visualize where the opening
is to be done thru the wall. Center
of the opening should be at about
23 ½‘’ above the base of the stove;

Note: Horizontal run should have a
slope of ¼ in per foot.

3. Make a 10-1/2" x 10-1/2" opening

in the wall, 23-1/2" inches in order
to introduce the radiation shield
thru the wall;

4. Cut the radiation shield to length if

necessary and install as shown.
Secure with four #10 x 1” wood
screws;

5. Install the vent terminal (13) with

2½ screws (12). You may want to
remove the vent casing for easy
access and manipulation, Keep
only in place the wall plate;

Floor Installation Details

6. Insert the 8 in. pipe into the round

opening of the interior black wall
plate (7). Fix the insulation pad (9)
around the 8 in. pipe with the
aluminum tape;

7. Keeping the insulation joint of the

8 in. pipe down, insert it into the
vent terminal wall plate;

8. Secure the 8 in. pipe to vent

terminal wall plate with the metal
screw;

9. Fix finally the vent terminal wall

plate with six 2 ½ in screws (12).

10. Insert the 4 in. flexible pipe (3) into

the 8 in. pipe and fix it to the vent
terminal flange. Use high
temperature silicone and one
locking band to secure it in place;

NOTE: All joints must be sealed with
RTV silicone, 315

°C. (600°F)

temperature resistance.