1 equipment check, Seal chamber requirements figure 3 – Flowserve Pac-Seal Type 51 User Manual

Page 4

Advertising
background image

1 Equipment Check

1.1 Follow plant safety regulations prior to equipment disassembly

including, but not limited to, the following:

• Lock out motor and valves

• Wear designated personal safety equipment

• Relieve any pressure in the system

• Consult plant MSDS files for hazardous material regulations

1.2 Disassemble pump in accordance with equipment manufacturer’s

instructions and remove sealing arrangement.

1.3 Check Seal documentation for seal design and materials of

construction.

1.4 Check shaft or pump sleeve outer diameter (OD), seal chamber

depth, and seal chamber bore to ensure they are dimensionally

within the tolerances shown on the seal assembly drawing.

(See Figure 3)

4

Sleeve or shaft finish to be

1.6 μm (63 μinch) R or better

a

Shaft or sleeve OD

-0.050 mm (-0.002 inch)

• Bearings must be in good condition

• Maximum lateral or axial movement of shaft (end play) = 0.25 mm (0.010 inch) FIM

• Maximum shaft runout at face of seal housing = 0.05 mm (0.002 inch) FIM

• Maximum dynamic shaft deflection at seal housing = 0.05 mm (0.002 inch) FIM

• Verify proper shaft and bore lead in chamfers are present and within specifications.

Difficulty and damage can be observed during seal installation without proper

lead in chamfers.

Seal Chamber Bore

-0.050 mm (-0.002 inch)

Seal Working

Height

Mating

Ring

Width

Seal Chamber Requirements

Figure 3