Installation – Flowserve SMK 22 User Manual

Page 10

Advertising
background image

0

Attention

Only qualified welders certified e. g. according to DIN EN 287 may weld the steam trap

into pressurized lines.

A subsequent heat treatment of the welds is not required.

Heat treatment of welds

. Observe correct position of installation.
2. Observe direction of flow. The flow arrow is on the trap body.
. Consider space required for opening trap. When the trap is installed a minimum space of

30 mm is

required for removing the regulating membrane

4 / /.

4. Remove plastic plugs. They are

only used as transit protection.

5. Clean butt-weld ends.
6. Apply arc welding processes  and 4 in accordance with ISO 406 or gas welding process 

to ISO 406.

Design with butt-weld ends

Installation

The trap can be installed in any position. Observe arrow indicating direction of flow. When mounted in

a vertical line with downward flow the trap is self-draining.

SMK 22, SMK 22-51